Example. Build a calendar plan for heating and ventilation of the workshop, if the directive installation period is 10-15 days.
Solution. Based on the volume of work, we make calculation for installation work on heating and ventilation of the workshop. According to the calculation, labor costs were received: by heating — 144.4 people. DN., in ventilation —133.2 people. DN.